The timetable for the biggest transformation of Glasgow’s public realm in half a century has been revealed.

In what will be the most significant change to city centre streetscapes since the 1970s pedestrianisation of Buchanan Street, work on the creation of 11 ‘Avenues’ will kick off in early 2025.

Funded through the City Deal and other Government streams, the programme involves the transformation of major thoroughfares including Argyle Street, the Broomielaw and Clyde Street, as well as George Square and surrounding streets.

The reworking of Sauchiehall, Pitt and Cambridge Streets is already nearing completion, but the new phase will see a major acceleration and expansion of the Avenues across the city centre. 

READ MORE: First look at final design for new George Square as revamp timetable revealed

As well as transforming "the look and feel of many key streets", the Avenues will be "a catalyst for continuing investment and economic growth, in addition to creating an environment to help increase the city centre residential population", Glasgow City Council said. 

They will also be "critical" to Glasgow’s Net Zero ambitions "by handing over more space to pedestrians and active travel, creating more city centre green spaces and equipping streets to better cope with flood risks with hundreds of new trees improving drainage", the council added.

Councillor Angus Millar, City Convener for City Centre Recovery, said the transformation would help deliver on the ambitions for the city centre, with benefits Glasgow would enjoy for decades to come. 

He said: “Our city centre has undoubtedly been impacted in recent years by multiple and overlapping challenges, from the legacy of the pandemic, fires, and absentee property owners to the shift to online retail and cost-of-living and inflation crises.

The final design for the new George Square The final design for the new George Square (Image: Glasgow City Council)

“But it’s increasingly a focal point for major investment, for population growth and we have a responsibility to nurture that and create the cosmopolitan feel Glasgow deserves.

“We know from our own past that when we make these changes, Glasgow has flourished.  The pedestrianisation of Buchanan Street in the 1970s was the catalyst for it becoming one of the most successful streets on these islands. But it also signalled the transformation of Glasgow away from its post-industrial past.

“We’re experiencing a similar period of transition just now and the Avenues can be the foundations for a city centre which gives people more reasons to visit, to invest in Glasgow and to make the city centre their home.”

Design work on 14 individual Avenues projects is progressing, with construction work set to begin in early 2025. Notably, this includes the closure of George Square and commencement of works on surrounding streets, as well as the reconfiguration of the eastern end of Argyle Street.

Work on a number of the projects will extend onto the later months of 2027, including High Street and Broomielaw/Clyde Street. The George Street to Duke Street Avenue will be completed in 2028.

Duke Street Avenue Eastern section towards Meat MarketDuke Street Avenue Eastern section towards Meat Market (Image: Glasgow City Council)

Throughout the works, the council will have the Get Ready Glasgow information portal, used during major events, in place to keep residents and businesses informed and to provide points of contact for queries and updates.  Some of the works will also be in place in the build-up to, and during, the 2026 Commonwealth Games.

Councillor Ruairi Kelly, City Convener for Neighbourhood Services and Assets, said: “The Avenues roll-out has already been delayed by the pandemic so it’s critical that we push on with the transformation of the city centre.  There will of course be some disruption but we’re putting in place the foundations for the next century and can assure Glaswegians that the hassle will be worth it.

“And right throughout the process we’ll ensure residents and businesses are kept informed of progress and disruption is kept to a minimum.”

The planned works have been welcomed by business leaders, major developers, employers and city-based organisations.

READ MORE: Sauchiehall Street phase of Avenues revamp to start this month

Stuart Patrick, Chief Executive of Glasgow Chamber of Commerce, said the business community welcomed the scale of the investment which would enhance the city’s look and feel while making it more attractive for visitors, investors, and workers. 

He added: "The next phase of the Avenues project is crucial for repositioning Glasgow to meet modern economic needs. While some disruption is inevitable, we are working with Get Glasgow Ready to keep businesses fully informed.  We encourage all businesses to engage with the programme to minimise any impact and ensure a smooth transition."

Property developers Moda Group, which is behind the 430-home Holland Park development near Charing Cross, contributed £360,000 towards the Avenues Project along Holland Street and Pitt Street. 

Planning and Engagement Director James Blakey said residents, visitors and the wider community will benefit from the scheme.  He said: “The Avenues Project is a brilliant example of the long-term benefits that come from public and private organisations working collaboratively.”

Audrey Carlin, Chief Executive of Wasps Studios, which is transforming The Briggait Clydeside Market Halls into a vibrant riverside destination, said: “The Avenues Project aligns with our ambitions by fostering a more sustainable, accessible, and attractive city centre, encouraging people to explore and spend more time by the river.  Through reanimating our section of Clyde Street with markets, cafés, and events, we aim to make a significant contribution to Glasgow’s goal of a more pedestrian-friendly, vibrant city centre.”