Abandoning the 'green' fuel required for the 'eco-friendly' vessels at the centre of Scotland's ferry fiasco would prevent further delays to a launch to support lifeline services, the nationalised shipyard firm has confirmed.
Hopes of Ferguson Marine having the first of the ferries Glen Sannox ready for the summer timetable have been abandoned with the timeline for its long-awaited use to serve Arran not looking like happening till July at the earliest.
Nationalised Ferguson Marine, which is building two wildly delayed and over-budget ferries for operator Calmac warned at the end of December that there could be a further delay of two months as it was facing "supplier issues" which is delaying the commissioning of the vessels' Liquified Natural Gas (LNG) propulsion systems.
A further delay would push back the completion of Glen Sannox beyond its latest scheduled date of March, and would be expected to affect sister vessel Glen Rosa’s arrival on May 2025.
Before the supplier issue, they were working to a planned acceptance date for Glen Sannox of March 31 for Glen Sannox - which was two days after the summer timetable for 2024 was due to begin. Acceptance Glen Rosa was scheduled for May 31, 2025.
READ MORE: Call to save Ferguson Marine as fears grow over new ferries contract
That would have meant that the first vessels would be ready to use for Arran at the end of May, as after handover CalMac need two months to carry out preparations for taking on passengers, including familiarisation training and safety drills.
In a letter seen by the Herald, Ferguson Marine state that the risk assessment for commissioning the LNG system on Glen Sannox, "identifies supplier issues which may extend the PAD (Planned Acceptance Date) beyond March 31. If stopped this risk would be mitigated."
It went on: [Ferguson Marine] are contracted to deliver two dual fuelled ferries, this contract condition has not altered. Therefore, programme assumptions remain aligned to this deliverable."
The letter was in response to questions asked about what improvement would be achieved in delivery dates if completion and testing of the LNG systems were immediately suspended.
The latest hold-up has been blamed on a supplier delay around specialist pipework for LNG.
In an update to MSPs, the shipyard firm said the pipework arrived on site in January and the installation will be finished by mid-March - and that 10 weeks of commissioning and testing will be required before it can be approved for use.
The Scottish Government has previously said all systems – including the LNG propulsion – will need to be completed before the state-owned ferry and port-owning agency Caledonian Maritime Assets Ltd can take delivery.
As one of the two wildly delayed and over-budget Scotland's fiasco ferries begun a first round of sea trials on Tuesday, marking a first step toward what is hoped will be an eventual handover to support lifeline CalMac services, it emerged that Glen Sannox requires further unspecified dry dock work before any official handover happens. It is understood that for the current Glen Sannox sea trials there is no LNG use.
CalMac then has to carry out two months of familiarisation training and safety drills - taking the timeline towards July.
Plans for the introduction of the 'eco-friendly' vessels had already been thrown into new chaos as it has emerged two key Scots ports will not be capable of providing the 'green' fuel.
In what is being described as a "new ferry shambles", the Scottish Government confirmed that there is no budget to provide the necessary port facilities for LNG at either Ardrossan or Troon in 2024/25.
The Scottish Government-owned ferry operator CalMac has already been planning to use Troon rather than Ardrossan for the two ferries that will serve Arran. That was when it was hoped that the first of the vessels would be ready for passengers in the Spring of last year.
The dual-fuel ferries which were meant to be identical, were lauded by then First Minister Nicola Sturgeon as the 'sustainable' ferries that would "contribute to Scotland's world-leading climate change goals".= They were hailed as a step towards a greener future for Scotland's state owned CalMac ferry fleet as they were to be the first UK-built ships capable of running off liquefied natural gas, or LNG, as well as conventional diesel.
The vessels, still to be completed at Ferguson's were due online in the first half of 2018, with both now due to serve Arran, but are at least six years late, with costs expected to be quadruple the original £97m contract.
Glen Rosa was meant to be delivered to CalMac in August 2018, but that is currently scheduled for May 2025. Glen Sannox, was launched by Nicola Sturgeon nearly seven years ago.
The dates of arrival have been constantly in a state of flux as their construction has been plagued by design challenges, cost overruns and delays.
Meanwhile, Ferguson Marine say MV Glen Sannox's first trip under her own propulsion on Tuesday marks day one of the builder's sea trials.
The nationalised shipbuiliding firm says that during the initial tests, the vessel will gather pace, slow down and stop many times with a tug attached for safety. The first round will focus on testing the principal machinery on board and anchors will also be tested. Some testing has already been taking place at the yard's quayside.
If all goes well, on Wednesday and Thursday she is expected to make some longer trips up and down the river as far as Gourock.
Endurance tests - when Glen Sannox will operate at higher speeds for longer periods of time - will form part of a further trials programme scheduled after her dry-docking in April.
Bad weather in December meant Glen Sannox missed an earlier major milestone which forced executives to call off a planned trip to a dry dock.
MV Glen Sannox was due to be moved from her mooring outside the Port Glasgow shipyard to Dales Marine shipyard in Greenock for works but high winds prevented the journey.
It meant that the dry dock work had to take place just before the handover.
Tugs had been dispatched to help the ferry make the trip under her own propulsion to Dales Marine until the weather conditions meant that the move was called off.
The ferry was also originally due to travel under its own power last month but that also was cancelled due to bad weather.
It comes as ministers have been told to act urgently to save the nationalised firm as concerns grow about its future over grave fears that it will not get a vital ferry contract to build a fleet of seven lifeline ferries.
The Scottish Government has confirmed that no decision has yet been made to invest in the new wave of 'loch class' vessels which is already delayed.
And GMB Scotland, the biggest union at nationalised Ferguson Marine, fears that when a decision is made by ministers, it will announce the contract must go to a competitive tender - ruling out a direct award to the yard to safeguard hundreds of jobs.
Gary Cook, senior organiser at GMB Scotland said the start of sea trials is welcome but called on the Scottish Government to signal the start of a new phase for Ferguson Marine by awarding the yard an imminent contract for seven small CalMac ferries.
He said: “No one, apart from the islanders who have waited far too long, want these two ferries completed more than the workers.
“They have been blameless throughout this work and their skill and commitment is beyond question and they now want to ensure taxpayers begin to get value from money from their yard.
“That depends on securing a pipeline of work, starting with the small ferries.
“It makes no sense for a private operator to profit from the investment that has gone into this shipyard after all the pain that has been endured over the current contracts.
“This yard and these workers must be allowed to turn the page and move on to secure the shipbuilding legacy of the Clyde for generations to come.”
There are concerns that the Scottish Government is treating the loss-making yard very differently to its sister state-owned ferry operator CalMac as it has already decided that the preferred option for the next contract over the future of lifeline island ferry services was a direct award - closing the door on bringing in private operators.
And the Scottish Government has already ruled out, for the time being, ploughing a further £25m requested for the modernisation of their shipyard firm as part of a new business plan to secure a sustainable future beyond just the delivery of the two much-delayed and over-budget lifeline ferries vital for its hopes of getting the contract for the Small Vessel Replacement Programme.
The union, responding to speculation that ministers are in preliminary talks with prospective buyers of Ferguson Marine, has also said the yard should remain in public ownership with secure work until taxpayers secure a return on the millions already spent there.
Responding to news of the sea trials, CalMac chief executive Robbie Drummond said Glen Sannox would be one of several vessels joining the fleet in the coming years.
He said: “We are very much looking forward to welcoming MV Glen Sannox into the CalMac fleet.
“She will provide much-needed resilience to the Arran community, and will be the first of the six large vessels and 10 small vessels joining us over the next five years.”
David Tydeman, chief executive of Ferguson Marine said: "Glen Sannox confidently left the quayside under her own propulsion for the first time. She sounded her horn and began the first in a series of rigorous sea trials. We began with the anchor and moved onto propulsion and manoeuvring tests. This will continue for the rest of the week. I would like to thank my colleagues at the shipyard and the team at CMAL for their hard work in achieving this key milestone.”
Why are you making commenting on The Herald only available to subscribers?
It should have been a safe space for informed debate, somewhere for readers to discuss issues around the biggest stories of the day, but all too often the below the line comments on most websites have become bogged down by off-topic discussions and abuse.
heraldscotland.com is tackling this problem by allowing only subscribers to comment.
We are doing this to improve the experience for our loyal readers and we believe it will reduce the ability of trolls and troublemakers, who occasionally find their way onto our site, to abuse our journalists and readers. We also hope it will help the comments section fulfil its promise as a part of Scotland's conversation with itself.
We are lucky at The Herald. We are read by an informed, educated readership who can add their knowledge and insights to our stories.
That is invaluable.
We are making the subscriber-only change to support our valued readers, who tell us they don't want the site cluttered up with irrelevant comments, untruths and abuse.
In the past, the journalist’s job was to collect and distribute information to the audience. Technology means that readers can shape a discussion. We look forward to hearing from you on heraldscotland.com
Comments & Moderation
Readers’ comments: You are personally liable for the content of any comments you upload to this website, so please act responsibly. We do not pre-moderate or monitor readers’ comments appearing on our websites, but we do post-moderate in response to complaints we receive or otherwise when a potential problem comes to our attention. You can make a complaint by using the ‘report this post’ link . We may then apply our discretion under the user terms to amend or delete comments.
Post moderation is undertaken full-time 9am-6pm on weekdays, and on a part-time basis outwith those hours.
Read the rules hereLast Updated:
Report this comment Cancel